In following screens you will find a series of photographs that represent the basic process for installing an Envisor™ equipment screen. RTU (Rooftop Units) vary greatly in size, construction, and performance features. Our engineers will evaluate the RTUs specific to a jobsite, to determine if we need to provide any additional components to accommodate these features. We have designed the Envisor™ products to be versatile enough that they can be field modified for adapting to most minor unforeseen field conditions.
Each Envisor™ screen arrives as "knock down" kits that will require some field assembly of the structural components, i.e. Corner Assemblies, Midspans and Extensions. The RTU depicted in the following screens has 4 Corner Assemblies, no Midspans, and 2 Extensions.
* Approximate total man hours to install this unit : 8 man hours
Basic tools required: Level, tape measure, reciprocating saw, 3/8" and 7/16" wrench and sockets, cordless drill, 1/8" and 5/16" drill bits, 5/16" nut driver bit.
Some additional variables that need to be considered once an Envisor™ shipment has arrived:
* Unloading boxed and crated product from the delivery truck/trailer. Relocating product on to a roof.
* Associating screen product with the appropriate RTU. (Some locations may have several units).
* Envisor screen kits do provide assembly hardware. (Screws and Bolts necessary to assemble a screen).
* Large RTU installs will require at least 2 men; all jobs should be evaluated in terms of "Man Hours". Cost to dispose of discarded packaging and trash from the jobsite.